Construction of a Bulk Liquids Berth

DESCRIPTION:

Pructon were engaged to modify the fuel lines on the HMAS Coonawarra site.  Redundant fuel lines were located, checked to ensure there was minimal risk to personnel and the lines removed. Existing fuel lines were purged with water and detergent and flushed to ensure they were free of contamination.  The contaminated water was safely removed and disposed. Works were undertaken to fabricate and install new lines to incorperate new operational requirments. These lines were fabricated off site at our workshop facility and then installed onsite with some welds needing to be undertaken on live or existing lines.

Location: Darwin-NT

Duration: 6 Months

Value: $1m