Project Details
Structural steel within the process plant was required to strengthen the steel tank and piping, in addition to installation of a piping rack.
Concrete footings were added along with existing upgrades to take the additional piping and steel load. Structural steel and cleats were added to the structure by welded and bolted connections. Steelwork and welded areas were site sandblasted and painted once completed.
Scope of Work
- Off-site fabrication and surface treatment of structural steel
- Installation of structural steel and site welding
- Remediation of concrete footing and installation of new
- On-site sandblasting and painting
Client:
Rio Tinto
Location:
Gove Peninsula (Arnhem Land), NT
Year of Completion:
2018